The project will be delivered under a Design and Construct (D&C) contract model.
The Contractor must plan, design, stage and deliver the works so that Kirkland Road and Woodlake Boulevard remain open and operational throughout construction. Full road closures, closure of an intersection approach, removal or prohibition of any existing through or turning movement, and loss of access to or from Durack will not be permitted. All existing traffic movements in every direction must remain available at all times during construction.
Under this D&C contract, the Contractor shall engage independent consultants of appropriate qualification and expertise to satisfy the following four functions:
1. Contractor’s Designer
2. Independent Design Verifier
3. Independent Works Certifier
4. Independent Conformance testing
The reference design will be provided to allow tenderers to understand the preliminary design intentsite constraints and indicative quantitiesThe Contractor will be responsible for completing the detailed design, including optimisation of the proposed layout and integration of temporary traffic management measures that maintain both roads, all intersection approaches, all existing through and turning movements, and access to and from Durack throughout construction.
The scope of construction works includes, but is not limited to:
- Earthworks and drainage works
- Pavement construction and asphalt surfacing
- Street lighting and landscaping works, and
- Provision for an Intelligent Transport System (ITS) queue detection system, if required.
The Contractor’s program must include all design, independent verification, approvals, procurement, construction, testing, commissioning, certification and handover activities required to achieve this contractual milestone.
Tenderers will be required to demonstrate a clear delivery methodology, resourcing strategy and construction program that supports achievement of this milestone while keeping both roads open, maintaining every existing traffic movement in all directions, preserving access to and from Durack, and managing impacts on the surrounding community.